STAGE TWO: Week 2 Progress Update (with Photos and Video)

Week 2 is done and dusted – literally. The water truck has been put to good use as the trucks dumped hundreds of cubic metres on site and the end loader and roller levelled the platform. Some of you would have seen the photos and time lapse footage on facebook and the website. A camera has been mounted on the roof and one frame is taken each minute. It will remain there during the project to record progress, for all of us to enjoy. We can now see the auditorium foundation taking shape, complete with a slight slope where the fixed seating will be, and the raised sanctuary to the west.

This coming week, the pad will be completed and building set out and work on the piers will commence.